Shehu Dikko, who chairs the National Sports Commission, has refuted claims that the $1.2 million FIFA allocation for Kebbi State’s mini-stadium construction was misused.
During a Friday appearance on Channels Television’s Politics Today program, Dikko clarified that the funds were never physically received by any Nigerian entity, explaining that FIFA maintains direct control over such project financing.
“That is where people are getting it wrong; no one collected the money. I’m not here to defend the NFF; they can defend themselves.
READ ALSO: Pinnick denies financial misconduct allegations over FIFA Goal project in Kebbi
“But as the leader of sports in Nigeria, what happens to the NFF affects the entire sports ecosystem. So we need to set the record straight for people to understand how this works,” he said.
Dikko detailed FIFA’s operational framework, noting that the international body selects its own consultants, oversees contractual agreements, and compensates contractors without channeling funds through the Nigerian Football Federation (NFF).
“I was a manager of FIFA projects, and I know how FIFA works. Nobody collected the money because FIFA manages its projects directly. The NFF’s role is to provide the land and state what they want. FIFA then appoints consultants, goes through procurement, and pays the contractor directly to deliver the project,” Dikko said.
The NSC head emphasized that the project’s initial valuation dates back nearly a decade, explaining its approval came in 2015 with procurement processes starting the following year.
“This project is not $1.2 million of today. When it was approved in 2015, the value was about ₦300 million. That was what the project was worth at that time,” he explained.
According to Dikko, complications with securing and documenting the land resulted in the foundation work and contract formalization being delayed until 2020, when FIFA’s selected contractor began construction.
“Before the project was signed, there was a public tender and procurement process. People just see a picture and assume it’s incomplete. That structure shown was only the first phase of the project,” Dikko stated.
The Birnin Kebbi facility, financed through FIFA’s Forward Programme, has attracted significant attention after drawing criticism regarding its construction quality and cost-effectiveness.
Public controversy intensified when FIFA featured the stadium in its social media imagery, triggering widespread disapproval and demands for official inquiry.
Dikko maintained that FIFA holds full accountability for project implementation, emphasizing that financial management adhered to transparent international protocols.
The House of Representatives Sports Committee has launched an inquiry into how the NFF handles FIFA and CAF developmental funding, with particular focus on the Kebbi facility.